Septic Tank Design

Value

Pre 285

Per 285

Daily flow

1080 gpd

420 gpd

Area of field

5191 sf

2100 sf

Pretreatment

2250 gallon

475 gallon

Treatment Capacity

0 gpd

500 gpd

Pump Tank

1000 gallon

750 gallon

Observed life span

15 + years

3 – 8 years


Let's consider one real life example:
Residence in Austin, TX 78734
5,164 sf residence with an Aerobic/drip system
Class II soils placed over fractured rock
Area known for groundwater problems

Determination of Design Flow, Q:
Pre 285:
0 - 1500 sf 2 BR
1500 – 1900 sf 3 BR
800 sf = additional BR
1900 sf = 3 Bedrooms
(5164 – 1900) / 800 = 4.08 additional bedrooms.
Must round up to 5 additional bedrooms.
Number of Bedrooms = 3 + 5 = 8 Bedrooms
Q = (B + 1) x 120 gpd (with a 20% credit for low flow fixtures)
Qpre-285 = (8 + 1) x 120 gpd = 1080 gpd.
Per 285:
Table III, says less than 5500 sf is 6 Bedrooms.
6 Bedrooms, Qper-285 = 420 gpd.

Determination of Field Area:
Pre 285:
No specific guidance on drip, but
Generally accepted Ra < 0.1 gpd /sf
A = Q / Ra = 1080 / 0.1 = 10800 sf
Per 285:
Fractured rock, Ra = 0.2 gpd / sf
A = Q / Ra = 420 / 0.2 = 2100 sf
Note: Area provided = 2600 sf

Sizing of Tanks:
Pre 285:
Q = 1080 gpd
Pretreatment = 1000 gallon single compartment tank
Treatment = 1250 gpd
Pump tank = 1000 gallon single compartment tank, minimum
Per 285:
Q = 420 gpd
Pretreatment = 475 gallon
Treatment = 500 gpd
Pump tank = 750 gallon

Let's consider another real life example:
Residence in Austin, TX 78734
5,164 sf residence with an Aerobic/drip system
House built on fractured rock
Area known for groundwater problems

Determination of Design Flow, Q:
Pre 285:
0 - 1500 sf 2 BR
1500 – 1900 sf 3 BR
800 sf = additional BR
1900 sf = 3 Bedrooms
(5164 – 1900) / 800 = 4.08 additional bedrooms.
Must round up to 5 additional bedrooms.
Number of Bedrooms = 3 + 5 = 8 Bedrooms
Q = (B + 1) x 120 gpd (with a 20% credit for low flow fixtures)
Qpre-285 = (8 + 1) x 120 gpd = 1080 gpd.
Per 285:
Table III, says less than 5500 sf is 6 Bedrooms.
6 Bedrooms, Qper-285 = 420 gpd.

Determination of Field Area:
Pre 285:
LPD, ET sizing due to the lack of soil.
A = 31000 (1+ 8) / (70 – 16.25) = 5191sf (in two alternating fields)
Per 285:
LPD, Fractured rock, Ra = 0.2 gpd / sf
Theoretically, A = Q / Ra = 420 / 0.2 = 2100 sf
Realistically, A = 2100*5/3 = 3500 sf.

Sizing of Tanks:
Pre 285:
Q = 1080 gpd
Pretreatment
1250 + 4(250) = 2250 gallon dual compartment tank
Pump tank = 1000 gallon single compartment tank, minimum
Per 285:
Q = 420 gpd
Pretreatment = 475 gallon
Treatment = 500 gpd
Pump tank = 750 gallon



Previous Article : Septic Tank System - - Next Article : Septic Cleaner

Featured Articles
Providing Quality Service...Guaranteed In the Greater Austin Area of Travis, Hays, Williamson, Burnet, & Bastrop Counties , Hudson Bend, Volente, Westlake Hills, Buda, Kyle, San Marcos, Florence, Brushy Creek, Leander, Misc Locations, Bell County.
Call (512) 338-1804 for fast, dependable service.
Seller Says "Too Bad" Seller Says “Too Bad” After Homebuyers Find Rotting Septic Tank Under Plywood (From Pumper Magazine, October 23, 2018) A news organization in Cortland Manor,...
Why Stay On A Septic System? Top 5 Reasons for Preserving Onsite as a Viable, Even Preferred, Sewage Management Option: Better protection of public health is possible ...
Septic Tank Additives There are many companies promoting their septic tank additives, saying they can solve all of your septic woes. For over 15 years, these claims have...
  • Septic Leach Field The leachfield is the most important and the most sensitive part of your septic system. It is...
  • Septic Tank Cost You are responsible for maintaining your system. You may wish to hire a professional to make sure your...
  • Septic Tank Care Learn about your household sewage system. Obtain and keep a sketch of the system with a detailed record...
  • Septic Pump Pumps: Accessories, Miscellaneous: STEP (septic tank effluent pumping) PVC pipe, fittings Grinder Pumps & Small Lift...
  • Septic Soil Why rock isn't “suitable soil”. There is much confusion being created by practitioners in the OSSF industry...